Energy Transfer did not immediately respond to a request for comment. The charges it faced were against the company itself, not individuals at the company. Before the charges were filed, the company acknowledged in an earnings report that the attorney general had been looking at “alleged criminal misconduct involving the construction and related activities of the Mariner East pipelines.” The company said it was cooperating but that “it intends to vigorously defend itself.”

As part of the plea, Energy Transfer is required to remediate and restore damaged water supplies. People who believe their water to be impacted will get free testing from an independent party. The Attorney General will hire independent professional geologists with no connection to the company to perform a review.

Energy Transfer will spend $10 million to restore waterways damaged by its construction. The Attorney General’s office says that is more than six times the maximum penalty required under state law. Under the Pennsylvania Clean Streams Law, penalties for these charges would have amounted to just $1.45 million.

When announcing the October charges, Shapiro called on the state legislature to toughen enforcement standards and fines, and said the Department of Environmental Protection “at times failed” to protect residents.

He highlighted the testimony of Rosemary Fuller of Delaware County, whose daughter was hospitalized after drinking water contaminated by Energy Transfer’s pipeline construction. The company had told her nothing was wrong with the water, but testing revealed E. coli and fecal coliform bacteria. Fuller’s water has not been restored.

The grand jury also found the company used unapproved chemicals in its drilling mud.

Over the course of five years, DEP fined Energy Transfer more than $20 million for more than 120 violations that stretch along the 350-mile-long pipeline, which travels through 17 counties, crosses 2,700 properties, and cuts beneath 1,200 streams or wetlands.

It carries volatile natural gas liquids from Marcellus Shale fields in Ohio and western Pennsylvania to the Marcus Hook industrial complex in Delaware County, Pa. Construction of the three-line project began in February 2017 but became mired in legal challenges and mishaps, was subject to a number of consent decrees resulting from citizen lawsuits, and was completed in February, several years behind schedule.



Read More: Energy Transfer held criminally responsible for damage from Mariner East pipeline construction

2022-08-05 02:00:00

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More

Privacy & Cookies Policy
%d bloggers like this: