SIMEC Atlantis Energy Limited says tidal turbine up and running off coast of Japan
It took nine weeks to assemble and test the turbine before it was shipped to Japan.
The tidal turbine clocked its first 10MWh (megawatt hours) of generation within the first ten days of operation and is now producing clean electricity in Japan, SIMEC Atlantis said.
The project included leasing tidal generation equipment and providing offshore construction services to Kyuden Mirai Energy for a pilot turbine located in the straits of Naru Island, within the southern Japanese Goto island chain. The SAE designed and manufactured AR500 tidal turbine was assembled at SAE’s operations and maintenance base at Nigg Energy Park in Scotland. The turbine was assembled and tested in nine weeks before shipping to Japan.
“This is a huge milestone for the deployment of clean, renewable energy from tidal stream and we hope it will be the first of many tidal turbines installed in Japan,” said Graham Reid, the chief executive officer of SIMEC Atlantis.
NO INVESTMENT ADVICE
The Company is a publisher. You understand and agree that no content published on the Site constitutes a recommendation that any particular security, portfolio of securities, transaction, or investment strategy is…
In exchange for publishing services rendered by the Company on behalf of SIMEC Atlantis Energy named herein, including the promotion by the Company of SIMEC Atlantis Energy in any Content on the Site, the Company…
Read More: SIMEC Atlantis Energy Limited says tidal turbine up and running off coast of Japan
2021-02-15 01:21:00